Network Rail accepts final conclusions of interim review


keywords: click to search
Office of the Rail Regulator
interim reviews
ORR
track access charges



Phrases in [single square brackets] are hyperlinks in the original document

Phrases in [[double square brackets]] are editorial additions or corrections

Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)


Network Rail

Network Rail accepts final conclusions of interim review
_______________________________________________________________


date
5 February 2004
source Network Rail
type Press release

note PR04007


Network Rail today formally accepted the Office of the Rail Regulator’s final conclusions of the Interim Review of track access charges. The Rail Regulator has determined that Network Rail’s expenditure on operations, maintenance and renewals over the next five years (Control Period 3) should be £22.2 billion. The settlement will provide Network Rail with secure, predictable revenues and put railway finances on a stable long-term footing.

The final conclusions are based on extremely challenging targets for improvements in efficiency and performance.

Network Rail recently announced the best quarterly performance for four years – a 26% reduction in delay minutes in the final three months of 2003. Total delay minutes for October – December 2003 were 3.3 million compared to 4.4 million in the same period the previous year. The future performance trajectory implies significant additional improvements in order to meet the overall targets in the next control period.

In terms of cost savings, the ORR has assumed efficiencies of more than 30% by 2008/09, and savings of 37% and 43% for 2007/08 and 2008/09 in respect of the West Coast Route Modernisation project. Network Rail is determined to deliver these targeted efficiency savings and is working to identify all the actions necessary to deliver the full savings.

The company is continuing its discussions with the SRA and ORR on the balance between grant and track access charges that make up its income. Network Rail’s accountability to its customers and the Regulator, which have been clarified and reinforced through the review, would not be changed as a result of any proposed unconditional grant.

Network Rail is also discussing proposals to reprofile an element of its revenue over the next two years. The company will submit its proposals to the Regulator around the end of February.

Commenting on the Board’s decision to accept the final conclusions, Ian McAllister, Chairman, said: “By accepting the Regulator’s final conclusions, Network Rail has committed itself to unparalleled improvements in performance and efficiency. In return we have gained certainty, stability and visibility regarding our future income.

“We face a significant challenge to deliver the scale of efficiencies demanded by this settlement. This will require change in every aspect of our activities. We have already begun this process and there can be no turning back.

“Network Rail’s performance is already showing welcome signs of improvement. We must now build on these visible signs of improvement and achieve sustained high levels of punctuality.”

-- ends -

Notes to editors
Network Rail is the 'not for dividend' operator of Britain's rail network. Our objective is to provide safe, reliable and efficient rail infrastructure.

We own and maintain the tracks, signals, tunnels, bridges, viaducts, and level crossings. We also own the network’s 2,500 stations, and manage the largest and busiest. We provide access to the tracks for every passenger and freight train, timetable their journeys, and operate the signalling, which controls their movements.

Network Rail is a company limited by guarantee with members instead of shareholders. It is run as a commercial organisation, but any operating surplus is re-invested in the rail network.
Our core focus is the operation, maintenance and renewal of existing rail infrastructure, with the Strategic Rail Authority taking the lead on enhancement projects.

We have set clear targets to improve performance and reduce costs, but safety is always at the forefront of our activities as we rebuild Britain's railway.

Details about Network Rail can be found on the Network Rail web site: www.networkrail.co.uk

For media enquiries: Network Rail press office on 020 7557 8292/3